The aforementioned division has completed works of:-
1- Two pipes were repaired with a size of(2.5 inches) and (90)mm type iron(polyethylene)in(Tanahi)complex,and a number of pipes were repaired with a size of(160 + 90 + 75 + 125)mm type(polyethylene)and a lock was replaced in (Mesirke)complex and installing a pipe with a size of(90)mm and length(150)m (Mesirke)complex.
2- A motor was replaced with a size of(18.5 kw),a pump (SP30-20), a cable with a size of(3*16),length(80)m,a pipe number(3)was with a size of(2)inches for well number(5)in semel district.
3- A breaker was replaced with a size of(400)amps in(Mesirke)water project, and a (6316 polyurethane motor)for a(75 kw)motor was replaced in(Mesirke)water project,(120) kg of(chlorine)were delivered to well number(6)(Mesirke + Dolba village’s well. +Bastake’s well).