Today On (10/9/2023)
The aforementioned division has completed works of:-

1- Installing and connecting a(90)mm ductile flometer to the Domiz camp’s well,numbered(1).
2- A pipe with a size of(90)mm type(HDPE)was maintenanced in(sitke)village and another pipe with a size of(75)mm type(HDPE)was maintenanced in(Hajaria)neighborhood in Domiz complex.
3- Two pipes with a size of(125+90)mm type(HDPE)were maintenanced in(Sharia)complex, along with repair of a(75)mm(HDPE)pipe in the center of Faida sub-district.
4- A lock was repaired with a size of(200)mm type(ductile)in domiz camp.
5- A starter was replaced with a a size of(15KW)for(chya daka)well numbered(5).
6- A (22KW)motor was replaced and an electricity cable with a size of(3*16)mm with a length of(100)m was replaced for the well(sitke)village.
7- A (250KVA)power transformer was repaired for(Sharya) project’s wells.
8- (6)samples were taken from faida’s wells and projects for the purpose of testing them in the laboratory of directorate of water outskirts duhok governorate.